DAILY REPORT INTERNSHIP WEEK 6 and WEEK 7

Assalamualaikum...

PROJECT     : PROVISION OF FRONT END ENGINEERING DESIGN (FEED) AND ENGINEERING, PROCUREMENT, CONSTRUCTION, INSTALLATION & COMMISSIONING (EPCIC) OF SK316 DEVELOPMENT PROJECT.
CLIENT        : PETRONAS CARI GALI SDN BHD. 
COMPANY   : ACTUAL BUILDER SDN BHD

(23 February 2015 : Monday)
Today, after attended weekly meeting, I follow Mr. Hafiz to check installation of insulation at CPP Technical Building. That was the first time I enters to the CPP Technical Building. I was so excited when enter to the building. What can I see that a lot of column have a big size and made from the steel.  Each column has their own calculation at the surface of the column. Besides that, I also can see the painting process. Before I can enter to the room that do the painting works, I need to make sure I'm wearing complete PPE (Personal Protection Equipment) for example, mask, goggle, ear plug and glove for safety requirements. This is to make sure I have safe from any hazard and risk that can causes injury.



Picture 1 shows installation insulation at lower deck and construction of foundation.





Picture 2 shows difference type support. Picture at the left side shows the support for structure and the right show the support for electrical cable.



Picture 3 shows the painting works.





Picture 4 shows the steel structure and steel column in the building.



Picture 5 show the big machine that cover by canvas to protect from damages and the pipe line at the CPP technical building.

(24 February 2015: Tuesday)
Mr. Roger asks me to do Summary of cold and hot water plumbing base on drawing that he gave to me. I have to ensure all the jointing that have in every system that state in the drawing and list all the jointing into the format that MMHE gave. 


Picture 1 shows the summary of cold and hot water plumbing and the 3D of pipe jointing using Autodesk Navisworks software.

(25 February 2015: Wednesday)
Help Mr. Azuan update progress report. After lunch hour, I continue doing the summary of cold and hot water plumbing.

Picture 1 shows S-curve of progress report. 


Picture 2 shows the 3D of pipe jointing drawing of pipe jointing at Living Quarters.

(26 February 2015 : Thursday)
I continue doing the summary of cold and hot water plumbing.


Picture 1 shows the 3D of pipe system at Living Quarters.

(27 February 2015: Friday)
Today I continue doing the summary of cold and hot water plumbing.

SUMMARY OF WEEK 7

 (2 March 2015: Monday)
Joint HSE Tool Box Meeting and attend site meeting with Mr. Hafiz at MMHE meeting room.
The issue that they discuss is about QA/QC documentation and progress in site (engineering). 

QA/QC issues:
1. Quality walkabout (fortnightly) is on Wednesday 18/02/2015 was Cancelled.
2. Submit installation procedure and testing method for Plumbing works (Press fit copper & PVC).
3. Submission of Weekly Progress Report by Wednesday 10 a.m. (Cut-off Friday). Submission of February’s Monthly Progress Report by 18/03/2015 (Cut-off 20/03/2015).

Engineering issues :
1. Plumbing pipes markings - ABSB to propose details by 05/03/2015 for approval.
2. Clashing issue between raised floor pedestals & E&I cable tray at TB.
3. STQ for detailed louvered wall rejected by PCSB. ABSB to resubmit details with single bend. 
4. Complete documents for hot water package – details for support/skid. (P&ID, GA, Datasheets).
i. 2 years spares list – ABSB to propose by 05/03/2015.

After lunch hour, I continue doing the summary of cold and hot water plumbing.

(3 March 2015 : Tuesday)
Help Mr. Azuan update progress report. After lunch hour I continue doing the summary of cold and hot water plumbing.


Picture 1 shows progress of CPP Technical Building and Wheel Head Platform.

(4 March 2015: Wednesday)
Today I continue doing the summary of cold and hot water plumbing.


Picture 2 shows drawing of pipe jointing.


(5 March 2015 : Thursday)
Today, I have toilet inspection with Mr. Andrew and Miss Fasya (Practical student KLMU). Mr. Andrew is the material controller for our company. Today, we inspect the toilet module for level 3 and level 4 for that have arrived at site yesterday. Total wet toilet module for level 3 and level 4 is 25 units. We have inspected 15 units of wet toilet for today. Before inspect the wet toilet, I have to prepared list of materials included with drawing for each type of wet toilet.  


Picture 3 shows inspection wet toilet with Mr. Andrew Material Controller ABSB).

(6 March 2015 : Friday)
Jacket will sail away within 4 or 5 days from now. Today they start to move the jacket using buggy to the foreshore. Buggy is one of the transportation that they use to move the jacket.  Buggy has a lot of tire and can lift the high weight. Usually buggy was controlled by operator by using remote; it’s easy to move the jacket that has 100 tons of weight. It has more than 10 tires to support and move the Jacket into the barge. 

Picture 4 shows the buggy controlled by buggy operator. 