PROJECT : PROVISION
OF FRONT END ENGINEERING DESIGN (FEED) AND ENGINEERING, PROCUREMENT,
CONSTRUCTION, INSTALLATION & COMMISSIONING (EPCIC) OF SK316 DEVELOPMENT
PROJECT.
CLIENT : PETRONAS CARI GALI SDN BHD.
COMPANY : ACTUAL BUILDER
SDN BHD
(23 February 2015 : Monday)
Today, after attended weekly meeting, I follow Mr. Hafiz to
check installation of insulation at CPP Technical Building. That was the first
time I enters to the CPP Technical Building. I was so excited when enter to the
building. What can I see that a lot of column have a big size and made from the
steel. Each column has their own calculation at the surface of the
column. Besides that, I also can see the painting process. Before I can enter
to the room that do the painting works, I need to make sure I'm wearing
complete PPE (Personal Protection Equipment) for example, mask, goggle, ear
plug and glove for safety requirements. This is to make sure I have safe from
any hazard and risk that can causes injury.
Picture 1 shows installation insulation at lower deck and construction
of foundation.
Picture 2 shows difference type support. Picture at the left
side shows the support for structure and the right show the support for
electrical cable.
Picture 3 shows the painting works.
Picture 4 shows the steel structure and steel column in the
building.
Picture 5 show the big machine that cover by canvas to protect
from damages and the pipe line at the CPP technical building.
(24 February 2015: Tuesday)
Mr. Roger asks me to do Summary of cold and hot water plumbing
base on drawing that he gave to me. I have to ensure all the jointing that have
in every system that state in the drawing and list all the jointing into the
format that MMHE gave.
Picture 1 shows the summary of cold and hot water plumbing and
the 3D of pipe jointing using Autodesk Navisworks software.
(25 February 2015:
Wednesday)
Help Mr. Azuan update
progress report. After lunch hour, I continue doing the summary of cold and hot
water plumbing.
Picture 1 shows S-curve of progress report.
Picture 2 shows the 3D of pipe jointing drawing of pipe jointing
at Living Quarters.
(26 February 2015 : Thursday)
I continue doing the summary of cold and hot water plumbing.
Picture 1 shows the 3D of pipe system at Living Quarters.
(27 February 2015: Friday)
Today I continue doing the summary of cold and hot water
plumbing.
SUMMARY OF WEEK 7
(2 March 2015: Monday)
Joint HSE Tool Box Meeting and attend site meeting with
Mr. Hafiz at MMHE meeting room.
The issue that they discuss is about QA/QC documentation and
progress in site (engineering).
QA/QC issues:
1. Quality walkabout (fortnightly) is on Wednesday 18/02/2015
was Cancelled.
2. Submit installation procedure and testing method for Plumbing
works (Press fit copper & PVC).
3. Submission of Weekly Progress Report by Wednesday 10 a.m.
(Cut-off Friday). Submission of February’s Monthly Progress Report by
18/03/2015 (Cut-off 20/03/2015).
Engineering issues :
1. Plumbing pipes markings - ABSB to propose details by
05/03/2015 for approval.
2. Clashing issue between raised floor pedestals &
E&I cable tray at TB.
3. STQ for detailed louvered wall rejected by PCSB. ABSB to
resubmit details with single bend.
4. Complete documents for hot water package – details for
support/skid. (P&ID, GA, Datasheets).
i. 2 years spares list – ABSB to propose
by 05/03/2015.
After lunch hour, I continue doing the summary of cold and hot
water plumbing.
(3 March 2015 : Tuesday)
Help Mr. Azuan update progress report. After lunch hour I
continue doing the summary of cold and hot water plumbing.
Picture 1 shows progress of CPP Technical Building and Wheel
Head Platform.
(4 March 2015: Wednesday)
Today I continue doing the summary of cold and hot water
plumbing.
Picture 2 shows drawing of pipe jointing.
(5 March 2015 : Thursday)
Today, I have toilet inspection with Mr. Andrew and Miss Fasya
(Practical student KLMU). Mr. Andrew is the material controller for our
company. Today, we inspect the toilet module for level 3 and level 4 for that
have arrived at site yesterday. Total wet toilet module for level 3 and level 4
is 25 units. We have inspected 15 units of wet toilet for today. Before inspect
the wet toilet, I have to prepared list of materials included with drawing for
each type of wet toilet.
Picture 3 shows inspection wet toilet with Mr. Andrew Material
Controller ABSB).
(6 March 2015 : Friday)
Jacket will sail away within 4 or 5 days from now. Today they
start to move the jacket using buggy to the foreshore. Buggy is one of the
transportation that they use to move the jacket. Buggy has a lot of tire
and can lift the high weight. Usually buggy was controlled by operator by using
remote; it’s easy to move the jacket that has 100 tons of weight. It has more
than 10 tires to support and move the Jacket into the barge.
Picture 4 shows the buggy controlled by buggy operator.