SUMMARY OF WEEK 4
PROJECT : PROVISION
OF FRONT END ENGINEERING DESIGN (FEED) AND ENGINEERING, PROCUREMENT,
CONSTRUCTION, INSTALLATION & COMMISSIONING (EPCIC) OF SK316 DEVELOPMENT PROJECT.
CLIENT : PETRONAS
CARI GALI SDN BHD.
COMPANY : ACTUAL BUILDER
SDN BHD
(9 February 2015: Monday)
Today I have attended HSE Tool Box Meeting with client
(PETRONAS) and MMHE. After finish tool box meeting i have joint Mr. Hafiz and
Mr Azuan in weekly site meeting at MMHE meeting room. In meeting room they have
discuss about progress site and the documentation. There are several problems
that they discuss to find the solution. One of the problems is double door at
WHP building. Foreman have measure the size of frame wrongly. The double door
that they order is little bit small from the size that foreman gives. The
solution is they have to add panel and welding it at the top of the door frame
to cover the hole before double door they were install.
After lunch hour, I help Mr. Hafiz (QAQC) prepare method
statement for MAPRESS Copper and make the demo report for MAPRESS Copper.
Diagram 1 shows the process of MAPRESS Copper.
(10 February 2015: Tuesday)
Today I have to prepare Hydro Test for UPVC pipe report.
In this test we use two type of pipe spool and label as Pipe
Spool A and Pipe Spool B as shown in picture 1.
Next, open all high point vent during filling of water. This is
to ensure no air is trapped. Start filling water from lowest point and let the
water overflow from the highest points. This is to keep air bubbles expelled
from the system.
Picture 2 : Fill in water into the Pipe Spool A and B. Set up
the Pipe Spool with Hydro Test Pressure Machine.
PIPE SPOOL A
a) We performed the hydro test for
the pipe. Initially, we maintain the test up to 9 bars and hold 3 minutes. We
start with 0 bars and continuous increase the pressure to 1, 2, 3, until 9 bars
withhold 3 minutes.
Picture 3 : Start with 0 bars and continuous increase the
pressure to 1, 2, 3, 4, 5, 6, 7, 8 and 9 bars withhold 3 minutes.
a) When it’s had reach until 9
bars, we found the leakage from the flange portion
Picture 4: Leaking at the flange portion.
After lunch hour, Mr. Azuan wants me to update progress work at weekly
progress report. Progress works must update every week and submit to MMHE by
Friday.
(11 February 2015: Wednesday)
Follow Mr. Hafiz to do
Joint Inspection with MMHE and client for wet box (Toilet). This wet box was
fabricated at factory and we need to inspect for make sure the wet box in good
condition after deliver at site. After done joint inspection, Mr. Azuan ask me
to measure the area for LQ building (wall and underside area).
Picture 7 shows the joint inspection for wet box with MMHE and client
(PETRONAS).
(12 February 2015: Thursday)
Today I have attended general HSE tool box meeting. After finish
Tool box meeting, Mr. Hafiz and I do the inspection for wet box (toilet
module). Total balance of wet box that we have to inspect is 16 boxes. This
inspection is only done by Mr. Hafiz and me with 2 people as a helper.
Picture 2 shows the inspection for toilet module.
(13 February 2015 : Friday)
Go to the site with Mr. Hafiz and see the welder doing welding
process. Mr. Hafiz explains to me about the welding test. There have 4 type of
welding test, which are UT, RT, MPI and DPI. UT test is used sound wave for detect
the weldment discontinuities. This testing is use high frequency sound to
penetrate the material.
SUMMARY OF WEEK 5
(16 February 2015 : Monday)
Today, during at site, I had seen lifting process at CPP
Technical Building. They want to lift machine that have weight more than a tone
from ground to the CPP Technical Building. What can I see is when lifting process,
all the safety officer, rigger and crane operator will work together to ensure
that no accident can happen.
Before machine can lift into the CPP Technical building, safety
officer will ensure all the straps are securely strapped in every corner of the
machine. When everything is ready, rigger will give a signal to the crane
operator and crane operator will slowly lift the machine. While machine are
lifted, rigger will blow the whistle so the entire worker will knows that they
are doing lifting process.
Picture 1 shows the lifting process at CPP Technical Building
(17 February 2015: Tuesday)
Today, our site team will lift the toilet module into the CPP
Living quarters. Before they lift the toilet module, all the safety officer,
rigger and crane operator will ensure the entire toilet module in a good
condition. Besides that, our supervisor will make sure the area of the Level 1
is free of obstruction such as wire support.
Picture 2: Ensure the area is free from an obstruction.
Picture below shows the lifting process for
toilet module :
(18 February 2015:
Wednesday)
I help Mrs. Asrah doing request token and update daily manpower
report. Today we work until 1.00 p.m.
(19 February 2015: Thursday)
Holiday: Chinese New Year
(20 February 2015: Friday)
Holiday: Chinese New Year