Assalamualaikum..
SUMMARY OF WEEK 2
PROJECT : PROVISION
OF FRONT END ENGINEERING DESIGN (FEED) AND ENGINEERING, PROCUREMENT,
CONSTRUCTION, INSTALLATION & COMMISSIONING (EPCIC) OF SK316 DEVELOPMENT PROJECT.
CLIENT : PETRONAS
CARI GALI SDN BHD.
COMPANY : ACTUAL BUILDER
SDN BHD
(Monday : 26 January 2015)
Today, Hj, Zainal taught to me that I need to be familiarized with the contract documents for project namely SK316. He want me to know about the details of project The client for this project is PETRONAS Carigali Sdn. Bhd. and the contractor is TMJV (Technip-MMHE Joint Venture). SK316 Gas Development Project is including Wellhead Platform (WHP), Central Processing Platform (CPP) with Living Quarters and a bridge linked Drilling Platform. This project has state at the MMHE East, Pasir Gudang. Besides that, I also help him to prepare the document for tendering.
(Tuesday: 27 January 2015)
I had attended the “Safety Induction Course” at E-Pass
One Stop Centre in Taman Mawar, Pasir Gudang. This course have two sections,
Section 1 is for understanding the important of safety at work place
and determine the hazard that have at the work place. Section 2 is examination.
We have to passes the examination to get the E-Pass. These courses were started
at 8.00 a.m. until 5.00 p.m.
(Wednesday: 28 January 2015)
Starting from today, I’m officially starting training at MMHE
East project. I have been introduced to Mr. Aizat as a Project Manager, Mr.
Azuan as Project Engineer, Mr. Hafiz as a QA/QC, Mrs Asrah as a site
clerk, Mr. Ah Long as a Foreman, Mr. Andrew as the Material controller and Mr.
Roger as a QC in plumbing services. Mr. Aizat explains the task that I need to
do every day. Every Monday morning, I need to attend the “Safety Tool Box” with
other workers. After that, I need to joint site meeting with PMC and client to
know about the progress work at the site.
Before I can enter to the site, I have to Attend Safety
Induction at Safety department. In this safety induction, they will give the sticker
for each worker to indicate that an employee understand about the importance of
safety in workplaces. This induction starts at 10.00a.m until 1.00 p.m.
(Thursday: 29 January 2015)
Mr. Azuan ask me to print and do the filing for weekly
progress meeting, weekly progress report and S Technical Query (STQ) include
with summary. STQ is the form that we need to get approval from the PMC and
client. For example, client want to have ice cream machine brand Panasonic, but
we cannot supply with that brand and we want to replace with another brand, so
we need to submit the proposal to them and get the approval to make sure they
are agree.
(Friday : 30 January 2015)
Mr. Azuan shows me the 3D
of the module. From the 3D I can see the overall view of the module. Now, they
divided into three module, which is Central Processing Platform Technical
Building (CPP TB), Central Processing Platform Living Quarters (CPP LQ) and Wheal
Head Platform (WHP). They separate into three part because it’s easy to manage
and construct the module.
Picture 1shows the 3D of module using Navisworks software
SUMMARY OF WEEK 3
Monday: 2 February 2015)
Today I help Mrs. Asrah to do the Request Token. This token is
to make sure our worker can enter to the site and to record into man power
system.
After luch hour, I go to the site with Mr. Azuan. He shows me
the CPP TB building, CPP LQ building and WHP building. He also explains about
the function of the each module. The works that our company do is architectural
part include insulation, supply furniture and install wall partition. Other
than that, we also do the piping and plumbing work.
Picture 1 shows the insulation at Living Quarters and CPP Technical
Building
Picture 2 shows the CPP Living Quarters.
(Tuesday: 3 February 2015)
I have follow Mr. Hafiz to do Joint Inspection for insulation
part at site. Firstly I need to prepare Request for inspection form for
insulation work. Secondly, prepare the drawing for inspection area and marking
the inspection area. The responsible people that have to do this inspection are
Mr. Salihudin from Petronas Cari Gali (PCSB), Mr. Khairul from MMHE and Mr.
Hafiz from Actual Builder (ABSB).
Picture 3 shows the insulation at CPP Living Quarters.
After site inspection done, Mr. Aizat ask me to prepare the
documentation that requested from site instruction form. Site instruction is
the form that MMHE give when they have any changes that need to change at site.
All the changes, our company will claim from the client. To make sure, they
approve the claim, we need to prepare the documentation as evidence.
(Wednesday: 4 February
2015)
I have follow Mr. Azuan and learnt more about
welding section. Today have Welding Qualification Test (WQT) at the workshop.
Before we start Welding Qualification Test, we need to check welder ID,
preparing the work area (set up the equipment), and then identify the type of
welding used (SMAW/FCAW) and recognize the position of welding (3G/4G). This
test was conducted for the whole day.
Every welder will do the test in the morning.
After done the welding test, welding inspector and client will inspected the
test piece by visual inspection. The result of the test will come out in the
evening. Usually, to make sure they pass the test (WQT), they have to make sure
the steel plat that they weld is neat and have no defect.
Picture 4 shows welder doing the Welding Qualification Test and
sample of Test piece that have done by them.
(Thursday: 5 February 2015)
Today, Mrs Asrah was MC, so I need to do her works. First of
all, I do the request token for new worker. Request token is the system that
MMHE created to make sure the worker for each subcon was record. If we do not
do this request token, the worker can’t enter into the site. This system must
update every 10 days, this is to make sure there is no redundancy.
Next, I help Mr. Hafiz to find the document that need to attach
into the site instruction form. For example, drawing, Technical Query (STQ),
report included picture before and after installation. This document is very
important to proof that we have done the works.
(Friday : 6 February 2015)
Submit the Site Instruction file to Mr. Aizat. Mr Aizat will
check and give to Quantity Surveyor to prepare the claim. Next, I have to
update daily manpower for today and yesterday worker. After done update, I
email to Mrs Yanti (MMHE engineer) and Miss Shima (Document controller at HQ)
for their record. In the evening, I follow Mr. Hafiz and Mr. Andrew go to
workshop and do the material inspection.
Picture 6 shows the material inspection at workshop.
No comments:
Post a Comment